About the Customer

The customer is a leading refinery in the Middle East with a processing capacity of 50,000 barrels/day. Specializing in the production of diesel and naphtha, the refinery operates on SAP S/4HANA 1610, leveraging SAP BW and an RBI solution for data analytics and risk-based inspection.

Business Scenario

STO management relied on multiple tools—SAP, Primavera, Excel, and various reporting systems—creating data silos and inefficiencies. Coordinating 50,000+ activities and 2,000+ temporary staff within a 24-month planning and 35-day execution window required seamless integration and real-time tracking.

Challenges

Operating with fragmented tools and disconnected systems, the refinery struggled with data inconsistencies, resource underutilization, and lost project learnings that extended turnaround durations and increased costs.

  • Multiple Tools Led to Data Inconsistencies – Using SAP, Oracle Primavera P6, and Microsoft Excel created fragmented processes, data silos, and version control issues across turnaround planning and execution.
  • Difficulty Identifying and Managing Open Orders in SAP – Lack of visibility into work order status made it challenging to track completion, identify bottlenecks, and manage dependencies.
  • Challenges in Defining Work Packs – Complex coordination between internal teams and contractors made work pack definition difficult, leading to unclear responsibilities and scope gaps.
  • Lack of Real-Time Updates – Absence of alerts and notifications reduced agility, causing delayed responses to critical issues during the 35-day execution window.
  • Underutilization of Resources – Poor resource visibility and planning tools affected efficiency in deploying 2,000+ temporary staff and production resources.
  • Delays in Activities Extended Project Duration – Activity delays cascaded through the schedule, extending the overall turnaround beyond the planned 35-day window.
  • No Updated Equipment History in SAP – Equipment modifications and maintenance performed during turnarounds were not systematically captured, limiting future planning accuracy.
  • Lost Project History and Learnings – Absence of structured knowledge capture from past STO executions prevented continuous improvement and repeated past mistakes.

Solution

Built using Procify, our AI-powered low-code/no-code platform.

After thoroughly assessing the customer’s needs, Procify implemented STO Manager, a comprehensive all-in-one solution within SAP, streamlining scoping, planning, and execution with offline-supported mobile technology.

  • End-to-End STO Management – Deployed single SAP-integrated solution covering scoping, planning, execution, and reporting, eliminating need for Primavera and Excel while maintaining all data within SAP.
  • Built-in Reporting – Provided ready-to-use and customizable reports offering real-time insights into project status, resource utilization, critical path, and cost tracking.
  • Flexible and Scalable Architecture – Built configurable and extendible platform adapting to evolving turnaround requirements, contractor workflows, and regulatory compliance needs.
  • Seamless SAP Integration – Ensured no external integrations required with all data staying within SAP S/4HANA for enhanced security, data consistency, and simplified IT support.
  • Mobile-Enabled Field Access – Implemented offline-supported mobile technology with multi-device compatibility, enabling field teams to work seamlessly in low-connectivity refinery environments.
  • Enhanced Usability – Designed intuitive UI with features like attachments, voice enablement, barcode scanning, and simplified navigation reducing training requirements.
  • Advanced Functionalities – Included Task List Master, Issue List, Learning Module for knowledge capture, Readiness Score tracking, Risk Matrix visualization, and work pack management capabilities.

Business Impact

  • Optimized Utilization of Production Resources & Tools (PRTs) – Better visibility and planning improved deployment of equipment, tools, and temporary staff.
  • Increased Wrench Time for Technicians – Digital tools and mobile access allowed maintenance teams to spend more time on actual work.
  • Reliable and Complete Equipment History – Systematic capture of turnaround activities created accurate equipment history for better future decision-making.
  • Simplified IT Support – Single SAP-based solution eliminated costly and complex integrations with external tools like Primavera.
  • Reduced Training Costs – Intuitive, user-friendly application minimized training requirements for internal teams and contractors.
  • Continuous Process Improvement – Structured learning module captured insights from past projects, preventing repeated mistakes and improving future turnarounds.