Key milestones of a Turnaround Project

Maventic
Posted on Jan 18, 2022

Key milestones of a Turnaround Project

Every turnaround be it minor or major can be challenging and some require years of thought before a formal planning can start. Planning for a turnaround begins with an evaluation of the previous events, the lessons learned and most importantly applying the learning to foster a smoother turnaround. This is still an easier process considering the hectic nature of events once the timelines are finalised. As every turnaround has a life cycle and it is imperative to define and track it while your organisation matures the turnaround solutions. Defining the right milestones helps in identifying and monitoring important phases of your turnaround plan. The table below illustrates the key phases and the key turnaround project milestones tracked in each phase as followed by several organisations.

ShutdownMSMilestones
Shutdown Strategy1Kick Off Meeting: Appoint a Shutdown Coordinator
 2Present & finalize the Shutdown Strategy Data Sheet
Front End Loading3First shutdown meeting. Contractors and activity owners (maintenance and project engineers) present their scope and review the lessons learnt from the last shutdown.
 4Internal scope review meeting held.
 5Procure Long lead materials
Detailed Planning6Capture and incorporate any unavoidable late work
 6Work Pack preparation
 7Freeze Scope of Work
 8Conduct Scope Optimisation Exercise – Lean thinking workshops
Pre Shutdown Work9Reconcile Materials
 10Issue signed approved shutdown handbook.
 11Plant Decommissioning / maintenance / Recommissioning / Clearance for operations
Post Shutdown work12Review actions taken. Transfer finding to shutdown lessons learnt spreadsheet.

There are several other important topics such as logistics, HSE and contracting/ procurement, which are just as vital to the successful execution of a turnaround as the others.

It is also a good practice to conduct a standard turnaround review typically by a third party . Such reviews can provide valuable insights on the progress of the above-mentioned key milestones. It helps assess the site’s preparedness and understand the potential risks that could negatively impact the planned cost and duration of the turnaround. A consistent and transparent approach coupled with a motivated team is what makes preparation successful on the front end.

This will ultimately lay the foundation for a successful yet safe execution as well.

maventic | Digital Forms

Related Articles

Stay up to date

Register to our blog updates newsletter to receive the latest content in your inbox.


    The information you provide will be used in accordance with the terms of our privacy policy.